| Activity Code |
Activity Name |
Agency |
Year of Imp. |
Status |
Remarks |
Strategy IN1, By 2007, Bhutan will have established a liberalised and competitive ICT infrastructure market |
| IN1.1 |
License new operators and service providers |
BCA
|
2006 |
Ongoing |
Licensed granted, Tashi InfoComm has been licensed in Nov 2006 as the second mobile operator in the country, Kuzoo FM 90 and Radio Valley FM 99.9 have been licensed to operate FM radio services. |
| IN1.2 |
Establish incentives for new ICT players to establish ICT business |
MoIC
|
2006 |
Ongoing |
Incentives provided, government support extended to call centres for connectivity and training |
| IN1.3 |
Promote FDI in ICT infrastructure development |
MoIC
|
2007 |
Not Started |
|
| IN1.4 |
Establish a coordination body to increase coordination amongst infrastructure providers. |
BCA
|
2005 |
Ongoing |
Coordination taking place among BPC and BTL |
Strategy IN2, By 2010, ensure an affordable, fast, secure, sustainable and appropriate ICT infrastructure throughout Bhutan |
| IN2.1 |
Deploy backbone infrastructure across Bhutan |
BT
|
2007 |
Not Started |
East-West SDH microwave link completed sometimes late 2005. The Gelephu-tingtibi-Trongsa-Jakar, and the Tingtibi-Pangbang-Nanglam-Pemagatshel-Gyelposhing- Mongar-Kanglung OPGW construction have been dropped subsequent to receiving indication from MoIC |
| IN2.2 |
Develop a plan for a countrywide connectivity to ICT infrastructure, including schools, Geog centres and villages |
MoIC
|
2005 |
Completed |
The broadband master plan has been completed for implementation in 10FYP |
| IN2.3 |
Establish Government-wide intranet connecting all agencies in Thimphu |
MoIC
|
2006 |
Ongoing |
|
| IN2.4 |
Extend Government-wide intranet to all Dzongkhags head quarters |
MoIC
|
2008 |
Ongoing |
Contingent to the backbone network |
| IN2.5 |
Extend Government-wide intranet to all geogs |
MoIC
|
2010 |
Ongoing |
Contingent to the backbone network |
| IN2.6 |
Establish multipurpose telecentres in every geog |
DIT
|
2010 |
Ongoing |
37 CIC's has been completed as of now.Each Geog will have a CIC by the end of 10FYP |
| IN2.7 |
Establish atleast 10 telephone connections in each Geog |
BCA
|
2007 |
Ongoing |
Almost completed, only few Gewogs are remained to be covered |
| IN2.8 |
Introduce and deploy advanced and appropriate technologies |
BCA
|
2006 |
Ongoing |
A pilot study is being carried out at Tangmachu in Lhuentshe for rural access trailing WIFI technology. |
| IN2.9 |
Explore ways of reducing cost of ICT hardware and software:
- Open source software;
- Re-cycling computers;
- Substitute processors; |
DIT
|
2005 |
Ongoing |
Local Assembled Computers being promoted. Also studying the effectiveness of using network computers. |